Hardware startup manufacturing: what decides the first production run, and it is rarely the engineering

A working prototype proves the product can exist. The first production run proves the company can make it again, on a date, at a cost. Between the two sit purchasing lead times, part choices made for the bench rather than the line, and a factory chosen before anyone knew the volume. Here is what to settle before you place the first order.

Hardware startup manufacturing goes wrong in a predictable place. The prototype works, the demo goes well, an investor or a first customer asks for a delivery date, and the founder gives one based on how long the engineering took. Then the first order goes to suppliers, and the real date arrives: whatever the slowest part takes to come in.

The pattern does not change with the product, whether it is an aircraft, a drone or an industrial machine. The engineering is usually ready before the purchasing, the parts list and the factory are. What follows is what to settle before the first production order goes out.

Why is a prototype not a product?

A prototype is built once, by the people who designed it, from parts bought one at a time from whoever had them in stock. A product is built repeatedly, by people who did not design it, from parts bought in batches from suppliers who have to deliver on time.

Almost every difficulty in the first production run comes from that difference. A part that was fine on the bench is out of stock for six months. A component chosen because it was the best is made in such small numbers that its price and delivery are set by someone else's demand. An assembly step that took the designer ten minutes takes a technician an hour without instructions.

Step 0. Design for the ten-thousandth unit, not the first

The most common mistake in hardware is not looking at scale. A product can work perfectly and still scale badly, or only at great cost: an expensive module, a component the team makes itself, or a step that needs a skilled technician's hands. At ten units, that is fine. At tens of thousands, it means a hundred scarce specialists or a part that never gets cheaper. Going from zero to one, keep the path from one to ten thousand in view: which parts can be bought in volume, which steps can be done by less skilled people or machines, and what each will cost at that volume. The same divide is set out for defense hardware in zero to one, one to a thousand.

Step 1. Find the part with the longest lead time

The delivery date of the first production run is set by the slowest part, not by the assembly time. Before promising a date, list every part, its supplier and its lead time from order to delivery, and sort by the last column.

At a Czech aircraft manufacturer the slowest part was obvious once written down. Every aircraft flew on a bought-in aviation engine with a lead time of six to seven months, which meant next year's engines had to be ordered in June, at prices expected to rise another 12% to 15%. Everything else in the plan could move; that order could not. The full story is in the Distar CZ engine story.

Step 2. Replace bench parts with volume parts

The best answer to a long lead time is often a different part, chosen from a category built in much larger volume.

At the same manufacturer, I wrote down what the engine actually had to do instead of choosing among the four aviation options: 110 to 120 horsepower, eight or nine litres an hour, under 75 kilograms dry, under $5,750 all in, delivered inside sixty days. Nothing in the aviation category met the list. A Škoda 1.0 TSI car engine, already flying on an aircraft since 2012, came in under $4,600, against up to $29,900 for the aviation options, and arrived in about sixty days. An engine made in the millions is cheap and available for the same reason its failure history is well understood.

Not every part has a high-volume twin. But for every expensive, slow part on the list, the question is worth asking: what does it have to do, and who makes something that does that in large numbers?

Step 3. Give every part one name and one supplier of record

A small hardware company often has the same part under three names: the designer's, the purchaser's and the supplier's. The same company that had three engine options had the same aircraft platform under three different product names in three markets. In production that turns into wrong orders, double stock and parts nobody can find.

Before the first run, the bill of materials needs one name per part, one part number, one approved supplier, and ideally a named second source for anything that would stop the line. It is dull work. Skip it, and the first run waits for a part that was ordered under the wrong name.

Step 4. Pick a factory for the volume you will actually order

Contract manufacturers are built for a volume. One built for tens of thousands will take a small first order, and put it behind every larger customer. One built for prototypes will take a large order and struggle to hold quality at that rate.

Choose for the next twelve months of real orders, not the plan for year three. If the factory's minimum order is above what you can sell, it can often be restructured; see how to negotiate a minimum order quantity. Ask the factory who else they build for at that volume, visit the line, and find out who on their side owns your order. The opposite problem exists too: a Prague manufacturer I worked with had its own 8,000 square metre plant and capacity for 150 unmanned aircraft a year that it was not using, because it was selling the work as parts on request. Unused capacity is often closer than a new factory; the account is in the Aviatex story.

Step 5. Price the hundredth unit before promising the first

The first units cost more than they will later: small batches, tooling, scrap and rework. An investor or a buyer will ask what the hundredth unit costs, and the answer decides whether the business works at all.

Build the cost of a unit at three volumes, the first run, one hundred and one thousand, part by part. Mark which parts fall in price with volume and which do not. The parts that do not fall are where the product's margin is decided, and they are usually the same parts with the longest lead times.

How long does it take to go from prototype to production?

For most hardware startups, at least as long as the longest lead time in the bill of materials plus the time to build, test and fix the first batch. In practice that is often six to twelve months from a working prototype, and longer for anything certified. The fastest way to shorten it is Step 2, not a faster factory.

When should a hardware startup choose a contract manufacturer?

Once the design is frozen enough that changes are the exception, and before tooling is ordered. Bring the manufacturer in early enough to comment on how the product is assembled; many cost and quality problems are cheaper to fix in the drawing than on the line.

What a ready first production run looks like

A bill of materials with one name, one supplier and a lead time for every part. The slowest part ordered first. Bench-only parts replaced or justified. A factory chosen for the volume you will really order, with a named person on their side. A unit cost at three volumes. With those in place, a production date stops being a guess. For defense hardware the same problem is in what breaks first between prototype and series production; for a hardware startup working through it now, that is the work on the startups page and, once you are in production, on the operations and suppliers page.