Contract manufacturing agreement checklist: the twelve terms to settle before the first order

A purchase order tells a manufacturer what to make this time. A contract manufacturing agreement decides what happens every other time: when quality slips, when a delivery is late, when prices rise, when you want to leave. Most problems with manufacturers are easier to solve because a term was settled in advance. Here are the twelve to settle, in plain language for the commercial side.

A contract manufacturing agreement checklist is worth more than any single clause, because most disputes with manufacturers come from something nobody wrote down. A purchase order covers one order. The agreement covers the relationship: what happens when quality slips, a delivery is late, a price rises or you want to move production. Below are the twelve terms to settle, in the order they usually come up. Your lawyer drafts and checks enforceability, especially across borders; the commercial decisions are yours.

1. Specification and approved sample

What exactly is being made: drawings, materials, tolerances, finishes, packaging, labelling. Attach an approved production sample as the reference the orders are checked against.

2. Quality standard and inspection

How quality is checked, by whom and where: the factory's inspection, your own or a third party's, and the acceptance criteria. Include the first article inspection before the first full run; how that works is in the supplier audit checklist.

3. Forecasts and firm orders

How your forecasts become firm orders, how far ahead, and how much of a forecast you are committed to. Manufacturers buy materials against forecasts; the agreement should say who pays if you change your mind, and whether you commit to any minimum annual purchase.

4. Prices and how they change

Prices at each volume, the currency, and the rules for changing them: how much notice, which costs can be passed through (raw materials, for example), and how often prices can be reviewed. Unwritten price rules become arguments.

5. Payment terms

Deposits, payment milestones, credit terms once trust is built, and the bank details process, including the rule that a change of bank details is confirmed by phone. Why that matters is in how to vet a manufacturer.

6. Delivery terms and late delivery

The shipping term (EXW, FOB, DDP and so on; see Incoterms explained for buyers) and who handles customs, lead times, delivery dates, and what happens when a delivery is late: notice, remedies, and when you may cancel. A clause about late delivery is easier to use than a conversation about it.

7. Tooling ownership

Who pays for moulds, dies and fixtures, who owns them, where they are kept and at whose storage cost, who maintains them, and the supplier's duty to release them to you, including if the supplier fails. This is the clause that decides whether you can ever leave.

8. Intellectual property and confidentiality

Your drawings, specifications and know-how remain yours and may be used only to make your product. Include confidentiality, and where relevant, terms that stop the manufacturer making or selling your product to others. Manufacturing abroad, ask counsel whether the protections are enforceable there.

9. Changes to the product or process

Neither side changes materials, components, sub-suppliers or the process without written approval. Most "it's the same, just cheaper" surprises are prevented by this clause.

10. Defects, returns and warranty

What counts as a defect, how quickly it must be reported, who pays for replacement and freight, and what happens with recurring defects. Set a warranty period for latent defects that appear after acceptance.

11. Liability and insurance

Who is responsible if a defective product causes damage or a recall, caps on liability, and the insurance each side carries. This is mostly counsel's territory, but the commercial question is whether the supplier can actually pay for a problem it causes.

12. Term, exit and transition

How long the agreement runs, how either side ends it, notice periods, and what happens on exit: last orders, stock and materials already bought, and the release of tooling and documents. A planned exit costs weeks; an unplanned one can cost the business.

What should not be left to the purchase order?

Anything that matters beyond one order: tooling, IP, changes, defects, price rules and exit. Purchase orders are fine for quantities and dates. They are a poor place for a relationship.

Who should draft it?

Counsel, with experience in the country where production happens. What the commercial side brings is the decisions: the volumes, the price rules, the quality standard, the late-delivery remedy and the exit plan. Settling those with you before the lawyer drafts is part of the work on the operations and suppliers page; how to choose the manufacturer in the first place is in how to find a manufacturer for your product.