Supplier audit checklist for a first production run: what to check on the floor, not in the brochure

A supplier audit before the first production run is not a tour of the factory. It is a check of whether the process that made your approved sample will make the next thousand the same way. Here are the eight areas I look at, the certificate check that takes five minutes, and the one document that tells you most.

A supplier audit checklist exists to answer one question before the first production run: will the process that made your approved sample make the next thousand units the same way? A factory tour does not answer it. Tours show the clean line, the newest machine and the certificate on the wall. An audit looks at what happens between them: where materials come in, how the work is set up, who checks it and what happens when something is wrong.

The checklist below follows the path a part takes through the factory, from the certificate on the wall to the first finished article.

Why audit if you already vetted the supplier?

Vetting answers whether the supplier is real and right for you: the legal entity, the factory, the references, the contract. That is covered in how to vet a manufacturer. An audit answers whether the supplier can make your product repeatedly to your specification. A real, honest factory can still be unable to hold your tolerance, or have no way of keeping your material separate from another customer's.

1. Is the quality certificate real, and does it cover your product?

Many suppliers show an ISO 9001 certificate. Check it, because a certificate can be expired, issued by an unaccredited body, or cover a different site or activity from the one making your product.

The check takes five minutes. IAF CertSearch, the database run for the international accreditation system, confirms three things at once: that the certificate is valid, that the body that issued it is accredited, and that the accreditation body is recognised. Search by company name or certificate number, then read the scope. If the certificate covers "distribution of electronic components" and you are buying machined parts, it does not cover your order.

A certificate proves a quality system exists. It does not prove your part will be right. The rest of the checklist is about your part.

2. How are incoming materials controlled?

Ask to see where raw materials and bought-in components arrive. Are they checked on arrival, against what? Are they labelled so that you can trace which batch went into which of your units? Is material that failed inspection kept physically apart? A supplier that cannot tell you which batch of material went into your order cannot tell you which of your units are affected when a batch turns out bad.

3. Is the process written down, and is it the one being followed?

Ask for the work instruction for a job similar to yours, then watch the job being done. The two should match. If the instruction is out of date or the operators work from memory, your first run will depend on who is on shift.

For your own product, agree before production which steps will be written down and approved: the setup, the critical operations and the checks. Any change to an approved process should need your agreement. That one clause prevents most of the "we changed the material, it's the same" surprises.

4. Does the work flow, or do people walk?

Stand on the floor for half an hour and watch one job. Is the layout laid out in the order the work is done? Does each worker have parts and tools at their station, or do they leave it to fetch something from another part of the shop? Every unnecessary walk is time, and time is cost and delay on your order. A well-arranged floor is usually a sign of an operation that runs well, and a well-run operation is what delivers on time at the quoted price.

5. Are measurement tools calibrated?

Look at the gauges and instruments used to check parts like yours. Each should carry a calibration label with a date, and the supplier should be able to show the record. A part measured with an uncalibrated tool has not been measured.

6. Where does inspection happen?

At the end of the line, on the line, or both? End-of-line inspection finds defects after they have been made, often in batches. Inspection at critical steps finds them while there is still something to fix. Ask what is inspected, how often, against which criteria, and who decides when a part fails.

7. What happens to a rejected part?

Ask to see where rejects go. They should be labelled, kept apart and recorded with a reason. Then ask what happens next: scrapped, reworked or sent back to the line? Reworked parts are where problems hide. Your contract should say whether rework is allowed on your product and, if so, how reworked units are identified.

8. Who owns your order on their side?

Not the salesperson. The person in production or quality who will know first when something goes wrong with your run and who will call you. Get the name, meet them, and agree how and how quickly they will tell you about a problem. A supplier without a named owner for your order will tell you about a problem when the goods arrive.

9. Does the first article match the drawing?

The first article inspection is the single most useful document in a first run. The supplier makes the first parts on the production process, with production materials, and measures every characteristic on your drawing, recording the actual value next to the requirement. In aerospace this is formalised in SAE's AS9102 standard; in the automotive industry, in the production part approval process. Outside those industries, ask for the same thing in plain form: every dimension and requirement, the measured result, pass or fail, signed.

A metrologist at the US National Institute of Standards and Technology measures a machined aluminium part with the probe of a coordinate measuring machine, the result shown as a deviation map on the screen
Photo: National Institute of Standards and Technology, Public domain, via Wikimedia Commons

Approve the first article before the rest of the run is made. If it fails, the run stops while the process is fixed, which costs days. If you find out on arrival, it costs the run.

What should a supplier audit report include?

One page per area above: what you checked, what you saw, and one of three findings: acceptable, acceptable with a corrective action by a date, or not acceptable. Attach the first article report and the certificate check. Agree the corrective actions with the supplier before you leave, in writing, with dates.

How often should you audit a supplier?

Before the first production run, after any significant change on their side (a new site, new owner, new key person or a changed process), and when your supplier scorecard shows defects or late deliveries rising. For a steady supplier with good numbers, once a year is usually enough.

What the audit leaves you with

A process you have seen, a first article you have approved, and a named person who will call you. That is the difference between hoping the first run matches the sample and knowing what it will take for it not to. For a hardware company going into its first run, the purchasing side is in hardware startup manufacturing; if you want the audit run with you, that is the work on the operations and suppliers page.